- Admin
- Dependency Lock
- Roadmap final meeting (WSP)
- All tasks needs to be wrapped up by end of June and invoicing completed by end of July
- August all remaining funds will be transferred over
- To work in July then we need money in hand by July, which means there is urgency to get funds from ActivitySim agencies
- Will submit "bridge task orders" of $10K for Task 2 type of work to continue work until all funds are set-up
- Within next month, suggest taking action to adjust the way we meet by setting up committees as outlined in Roadmap (with some potential adjustments)
- Dependency Lock
- Josie Kressner gave an introduction with her background
- Tested tool options, leading to final recommendation of using UV
- Provided demo on tool
- Installs quickly
- Can install using uv.lock or from PyPI, (or option 3, use Windows Installer)
- Provided demo on tool
- Future improvements
- Review and remove unused dependencies
- Some, but not all, Sharrow test are failing on Mac and Linux
- Estimation test is failing due to missing larch release on PyPI
- Benchmarking functions require code changes to remove Conda
- Remove Conda from all Jupyter notebooks
- Made documentation updates
- Jeff N to review pull request
- Roadmap
- Discuss on Tuesday, and maybe also on Thursday