Project Jellyfish weekly report

2025-09-09

Overview

  • Internal project set up
  • Repository public fork
  • Building & Testing
  • Specification review

Activity details

Plan for the next week

  • WP1: Add xttrocc architecture extension (Pierre-Emmanuel)

  • WP2: Add disassembler support for the ISA extension

    • Misc instructions (Pierre-Emmanuel)
    • Context switch instructions (Pierre-Emmanuel)
    • Address Generator instructions (Pietra)
  • WP3: Test the assembler and disassembler (Arthur)

  • Provide a specification document (Nathan)

Work package progress

  • WP1 - Extend the tool chain drivers
  • WP2 - Add assembler/disassembler support for the ISA extension
  • WP3 - Test the assembler and disassembler
  • WP4 - Add builtin function support for the ISA extension

Builtins completed: 0/70

Risk table

There are no updates to the risk table.

Planned absences

  • Arthur will be at Oxidize from September 16 to 18
  • Pierre-Emmanuel will be at Kangrejos from September 17 to 18
  • Pierre-Emmanuel will be on vacation from September 19 to 25
  • Pietra, Jeremy and Pierre-Emmanuel will be at GNU Tools Cauldron from September 26 to 28.

Time tracking

Work package This period Cumulative
WP1 Extend the tool chain drivers
WP2 Add assembler/disassembler support
WP3 Test the assembler and disassembler
WP4 Add builtin function support
Total