-
Notifications
You must be signed in to change notification settings - Fork 136
Durations and Progress
Here we will describe how project and phases duration and progress are calculated and what are their meanings.
-
Normal

-
Delayed

58 is Actual Duration (or current duration) - it is calculated using all active and completed phases:
- it includes delayed time for active phases
- doesn't include overlapped time twice
- include gaps between phases
65 is Planned Duration - it is calculated using all non-draft phases:
- doesn't include overlapped time twice
- include gaps between phases
- so basically it's difference between minimum
startDateof a phases till maximumendDateof phase (which are non-draft)
14 is Delay duration - it is calculated as a difference between Actual Duration and Planned Duration.
53% is Project Progress - it is calculated as average progress of all non-draft phases.
Example, if we have:
- Planned phase (progress
0) - Active phase with progress
17% - Completed phase (progress
100%) - Drast pahse (is not included in calculations)
Then Project Progress would be (0 + 17 + 100 / 3 = 39%).
Imagine we have 2 phases with a gap between them:
- Sep 1 - Sep 3 (3 days)
- a gap
- Sep 5 -Sep 7 (3 days)
The total project duration is calculated since Sep 1 till Sep 7 (8 days) including the gap, rather than just sum phases times.
Imagine we have 2 phase which overlap each other:
- Sep 1 - Sep 7 (8 days)
- Spe 4 - Sep 11 (8 days)
The total project duration is calculated since Sep 1 till Sep 11 (12 days) and doesn't calculates overlapping time twice.